Amending the Building Permit and Design During Construction

What to do when the investor, contractor or supervisor changes during construction, when the design changes, or when you cannot finish within the statutory deadline. The Law on Construction of Buildings distinguishes a notification to the inspector from a new building permit for the amended design.

7–30 daysDepends on the kind of design change5 steps

Checked against official sources: October 2026

If the investor changes during construction, the new investor files with the authority that issued the permit, within 30 days of the change, an application to amend the building permit to the new investor (Form 7). Attach proof of land rights (and rights to the building for reconstruction). The decision is made within 7 days, and the application can be filed until the use permit is issued (Art. 44).

Responsible: New investor
Deadline: Application within 30 days, decision within 7 days
Documents:
  • Application to amend the permit to the new investor (Form 7)
  • Proof of ownership or other right to the land (and the building in case of reconstruction)