Construction & Permits
Urban-Technical Conditions (UTC)
Obtaining urban-technical conditions — a mandatory prerequisite for project design and building permit.
5–35 days€30–1304 steps
eUprava — Urbanističko-tehnički uslovi
Zahtjev za UTU može se podnijeti elektronski putem portala eUprava. Potrebna je registracija i elektronski potpis.
1
Documentation preparation
Collecting property certificate, plan copy and proof of land rights.
Collecting property certificate, plan copy and proof of land rights.
Responsible: Investor
Deadline: 1–5 days
Documents:
Property certificatePlan copyProof of land rights
2
Submitting UTC application
Filling out and submitting the application to the competent authority.
3
Application processing
The competent authority reviews the application and determines conditions based on the urban plan.
4
UTC issuance
The competent authority issues the UTC decision with defined construction conditions.