Construction & Permits

Urban-Technical Conditions (UTC)

Obtaining urban-technical conditions — a mandatory prerequisite for project design and building permit.

5–35 days€30–1304 steps
eUprava — Urbanističko-tehnički uslovi

Zahtjev za UTU može se podnijeti elektronski putem portala eUprava. Potrebna je registracija i elektronski potpis.

1

Documentation preparation

Collecting property certificate, plan copy and proof of land rights.

Collecting property certificate, plan copy and proof of land rights.

Responsible: Investor
Deadline: 1–5 days
Documents:
Property certificatePlan copyProof of land rights
2

Submitting UTC application

Filling out and submitting the application to the competent authority.

3

Application processing

The competent authority reviews the application and determines conditions based on the urban plan.

4

UTC issuance

The competent authority issues the UTC decision with defined construction conditions.