Construction & Permits

Preparatory Works for Construction

Preparatory works (fence, site facilities, access roads, connections) may start only after the building permit and the construction start notification. The exception is objects of general interest in state ownership: for them the Government gives consent for preparatory works, and the application goes to the Ministry.

At least 7 days' notice to the inspectorNo administrative fee (Ministry consent)3 steps

Checked against official sources: October 2026

Official description of the procedure

eUprava — Notification of preparatory works

Service description (no fee provided for, legal basis, Ministry contact) and the form to download. The application is submitted at the authority's counter or by post; electronic submission is not available.

The investor may start preparatory works after the building permit is issued and construction start is notified to the construction inspector (Art. 38). They are carried out on the basis of a study with the site layout, type of fence, site facilities and access roads, crane and material delivery locations and site connections, together with an occupational health and safety plan and a construction waste management plan.

Responsible: Investor
Deadline: Before works begin
Documents:
  • Building permit
  • Construction start notification
  • Study on preparatory works
  • Occupational health and safety plan
  • Construction waste management plan
Note: If the investor carries out preparatory works contrary to Art. 38, the inspector orders the site to be closed (Art. 138). The content of the study is prescribed by the Rulebook on the content of the study on preparatory works.