Utility Connections

Connecting a building to the electricity, water and sewage networks. Each operator has its own conditions, forms and prices, so you apply to each separately.

Depends on the operator, usually several weeksDepends on the operator and connection capacity4 steps

Checked against official sources: October 2026

Official description of the procedure

CEDIS — Connection to the distribution system

CEDIS's official page with a step-by-step connection guide (technical conditions, opinion on the main design, connection agreement). Download the forms at: https://cedis.me/zahtjevi-i-ugovori/. The page does not mention electronic submission of the request.

The designer or investor requests connection conditions from the operators (CEDIS, water utility) in order to prepare the main design. If an operator does not reply within 15 days, it is deemed to agree with the UTC (Art. 8 of the Law on Construction of Buildings).

Responsible: Designer / investor
Deadline: Up to 15 days
Documents:
  • Request for technical conditions
  • UTC
Note: CEDIS states that it issues the technical connection conditions at the request of the competent authority (they become part of the UTC) and its opinion on the main design at the reviewer's request.