eParcela.me
Construction & Permits

Use Permit

The use permit confirms that the building was built according to the building permit and main design. Without it the building must not be used. It is issued by the authority that issued the building permit, and for a family house a contractor's statement is enough instead of a technical inspection.

About 1–3 monthsInvestor pays for inspection; fees vary by authority5 steps

Checked against official sources: October 2026

Official description of the procedure

gradjevinskadozvola.me — Ministry portal

The Ministry's guide to the building and use permit (third step: technical inspection and use permit), institutions' contacts and a chatbot. You do not submit the use permit application there; it goes to the authority that issued the building permit.

When works are finished, professional supervision prepares a final report that the building was built according to the reviewed main design (or as-built design). The report includes the as-built survey of a geodetic organization and the building's energy performance certificate (Art. 52).

Responsible: Professional supervision / contractor
Deadline: Upon completion
Documents:
  • Final supervision report
  • As-built survey (geodetic organization)
  • Energy performance certificate
Note: A single-family residential building has no supervision. The contractor gives a statement that the building was built according to the permit and main design and is fit for use.